Step by step, our fischer Energy Park in Achern-Fautenbach is taking shape.
First, the individual tower sections were prepared on the ground for assembly. Even at this early stage, the impressive scale that the two wind turbines will ultimately reach became clear.
Now, construction is moving upwards: section by section and metre by metre, the towers are rising into the sky. With each new section, the progress becomes more visible, gradually transforming the familiar skyline of our site.
Once completed, each of the two wind turbines will reach a total height of almost 250 metres. Together, they are expected to generate around 25 million kWh of renewable electricity per year, which will be fed directly into our plant.
This makes the wind turbines an important part of our energy concept in Achern-Fautenbach, combining renewable energy for our production operations with our plans for green hydrogen.